With it, you will be happy and relaxed to prepare for the exam.After the advent of the Passtcert latest Nokia Certification SDM_2002001050 dumps pdf, passing Nokia certification SDM_2002001050 exam is no longer a dream of the IT staff. All of Passtcert practice questions and answers about Nokia Certificationcertification SDM_2002001050 exam have high quality and 95% similarity with the real exam questions.
Share some Nokia Certification SDM_2002001050 exam questions and answers below.
What is the meaning of 'Staged Acceptance Procedure'?
A. It is a procedure used in rollout projects with separate customer acceptance milestones for Site Acquisition, Construction Works, Equipment Delivery, Telecom Implementation and Network Design.
B. It is a procedure in rollout projects where we limit Cluster Acceptance to only one cluster in the network, the so-called 'Golden Cluster'.
C. It is a procedure in rollout projects where several customer acceptances are accumulated so the number of separate customer invoices can be reduced.
D. It is a procedure where the customer accepts the network if he does not formally submit objections against acceptance.
Answer: A
NSN is under pressure to keep Customer deadlines but PO has not yet been received. Under what circumstances can a PO be issued to the subcontractor?
A. If the deadline is really critical for the Customer, PM must take the responsibility to execute the Rollout.
B. PM must escalate the issue and request for a formal approval from CT.
C. PM requests subcontractor to start work without NSN PO - that will be issued when we get out PO from the Customer.
D. PM will not subcontract services without a Customer PO.
Answer: D
What is the BEST timing to review the Estimate at Completion (EAC)?
A. During the planning phase, in order to anticipate all possible risks.
B. During project closure in order to consistently explain the Project results.
C. During the entire project lifecycle, typically once per month.
D. Each time the Cost and Progress Manager requests support to review cost deviations.
Answer: C
Do not spend too much time and money, as long as you have Passtcert Nokia Certification SDM_2002001050 dumps pdf you will easily pass the exam.Passtcert has a huge team of IT experts, who continue to use their knowledge and experience to study a lot of IT certification examination papers of past few years. Their findings of the research is now the product of Passtcert, therefore Passtcert Nokia Certification SDM_2002001050 dumps pdf are very similar with the real exam, which can help a lot of people to realize their dreams.
No comments:
Post a Comment